Hide Town Energy Storage (25INR0287)

Hide Town Energy Storage is a 102.8 MW other interconnection project in Scurry, Texas with a current status of operational. It is proposed to connect at 18555 Union Switch 138 kV .

102.8 MWCapacity
OperationalStatus
ScurryMarket
OtherTechnology

Project facts

Canonical nameHide Town Energy Storage
Queue ID25INR0287
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketScurry
TechnologyOther
Capacity102.8 MW
StateTexas
CountyScurry
Point of interconnection18555 Union Switch 138 kV
Requested (queue) date2023-01-17
Proposed in-service date
Operational date2029-10-11
Withdrawn date
DeveloperHide Town Energy Storage LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.