Hoskins 345 kV Substation (GEN-2023-SR6)

Hoskins 345 kV Substation is a 100.2 MW solar interconnection project in Wayne Co, Nebraska with a current status of withdrawn. It is proposed to connect at Hoskins 345 kV Substation.

100.2 MWCapacity
WithdrawnStatus
NEMarket
SolarTechnology

Project facts

Canonical nameHoskins 345 kV Substation
Queue IDGEN-2023-SR6
Statuswithdrawn
Source statusWITHDRAWN
MarketNE
TechnologySolar
Capacity100.2 MW
StateNebraska
CountyWayne Co
Point of interconnectionHoskins 345 kV Substation
Requested (queue) date2022-12-16
Proposed in-service date2024-12-31
Operational date
Withdrawn date2023-10-26
Developer
Utility / transmission ownerNPPD

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.