Hoskins-Twin Church 230 kV Line (GEN-2016-116)

Hoskins-Twin Church 230 kV Line is a 320.0 MW wind interconnection project in Dixon, Nebraska with a current status of withdrawn. It is proposed to connect at Hoskins-Twin Church 230 kV Line.

320.0 MWCapacity
WithdrawnStatus
NEMarket
WindTechnology

Project facts

Canonical nameHoskins-Twin Church 230 kV Line
Queue IDGEN-2016-116
Statuswithdrawn
Source statusWITHDRAWN
MarketNE
TechnologyWind
Capacity320.0 MW
StateNebraska
CountyDixon
Point of interconnectionHoskins-Twin Church 230 kV Line
Requested (queue) date2016-11-30
Proposed in-service date
Operational date
Withdrawn date2017-06-29
Developer
Utility / transmission ownerNPPD

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata