Infinium Solar is a 401.6 MW solar interconnection project in Howard, Texas with a current status of operational. It is proposed to connect at #1058 Longshore Switch - #18548 Prairieland Switch 345kV Ckt 1.

401.6 MWCapacity
OperationalStatus
HowardMarket
SolarTechnology

Project facts

Canonical nameInfinium Solar
Queue ID29INR0019
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketHoward
TechnologySolar
Capacity401.6 MW
StateTexas
CountyHoward
Point of interconnection#1058 Longshore Switch - #18548 Prairieland Switch 345kV Ckt 1
Requested (queue) date2024-08-16
Proposed in-service date
Operational date2029-07-01
Withdrawn date
DeveloperJackalope Flats Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.