Jarratt Energy Facility 2 (AF2-299)

Jarratt Energy Facility 2 is a 18.0 MW solar interconnection project in Greensville, Virginia with a current status of active. It is proposed to connect at Fields 34.5 kV.

18.0 MWCapacity
ActiveStatus
PJMMarket
SolarTechnology

Project facts

Canonical nameJarratt Energy Facility 2
Queue IDAF2-299
Statusactive
Source statusactive
MarketPJM
TechnologySolar
Capacity18.0 MW
StateVirginia
CountyGreensville
Point of interconnectionFields 34.5 kV
Requested (queue) date2020-03-30
Proposed in-service date2022-12-12
Operational date
Withdrawn date
DeveloperJarratt Energy Facility, LLC
Utility / transmission ownerDominion

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata