Keys Hollow Solar Phase II SLF (24INR0065)

Keys Hollow Solar Phase II SLF is a 200.8 MW solar interconnection project in Goliad, Texas with a current status of operational. It is proposed to connect at 345kV Tap 8164 Coleto Creek - 8673 RAPTOR7A.

200.8 MWCapacity
OperationalStatus
GoliadMarket
SolarTechnology

Project facts

Canonical nameKeys Hollow Solar Phase II SLF
Queue ID24INR0065
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketGoliad
TechnologySolar
Capacity200.8 MW
StateTexas
CountyGoliad
Point of interconnection345kV Tap 8164 Coleto Creek - 8673 RAPTOR7A
Requested (queue) date2021-06-17
Proposed in-service date
Operational date2028-03-10
Withdrawn date
DeveloperKeys Hollow Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata