Goliad County, Texas — Interconnection Projects
The interXdata warehouse tracks 23 interconnection projects in Goliad, Texas, representing 4,779 MW of requested capacity.
23Total projects
4Active
17Operational
1Withdrawn
4,779 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 10 | 2,107 MW |
| Other | 8 | 1,387 MW |
| Gas | 1 | 655 MW |
| Solar+Battery | 2 | 454 MW |
| Battery | 2 | 176 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Coleto Creek - Fuel Change Only | 26INR0664 | Gas | 655.0 MW | operational | Goliad, Texas |
| Coleto Creek | 6178_1 | Other | 622.4 MW | operational | Goliad, Texas |
| Diablo Campo Storage | 27INR0149 | Other | 313.5 MW | operational | Goliad, Texas |
| Peregrine Solar | 22INR0283 | Solar+Battery | 301.3 MW | operational | Goliad, Texas |
| Peregrine Solar | 65979_PSPV | Solar | 300.0 MW | operational | Goliad, Texas |
| Tulsita Solar | 21INR0223 | Solar | 256.2 MW | operational | Goliad, Texas |
| Ray Ranch Solar | 67837_RAYRS | Solar | 255.2 MW | active | Goliad, Texas |
| Kuy Creek Solar 1 SLF | 28INR0303 | Solar | 234.9 MW | operational | Goliad, Texas |
| Angel City Solar | 27INR0144 | Solar | 221.0 MW | operational | Goliad, Texas |
| Lucas Solar SLF | 24INR0384 | Solar | 204.1 MW | withdrawn | Goliad, Texas |
| Keys Hollow Solar Phase II SLF | 24INR0065 | Solar | 200.8 MW | operational | Goliad, Texas |
| KEYS HOLLOW SOLAR SLF | 24INR0067 | Solar | 200.8 MW | operational | Goliad, Texas |
| Eighteenmile Solar SLF | 24INR0061 | Solar+Battery | 153.1 MW | active | Goliad, Texas |
| Kuy Creek Storage 1 SLF | 28INR0304 | Other | 151.5 MW | operational | Goliad, Texas |
| PEREGRINE BESS | 23INR0206 | Other | 150.0 MW | operational | Goliad, Texas |
| Peregrine BESS 2 | 25INR0078 | Other | 150.0 MW | operational | Goliad, Texas |
| Double A Solar SLF | 27INR0248 | Solar | 132.6 MW | operational | Goliad, Texas |
| Myers Solar and Storage | 68172_MYEPV | Solar | 100.9 MW | active | Goliad, Texas |
| Coleto Creek ESS Addition | 22INR0275 | Battery | 100.1 MW | suspended | Goliad, Texas |
| Myers Solar and Storage | 68172_MYEBT | Battery | 75.7 MW | active | Goliad, Texas |
| Double A Storage SLF | 27INR0257 | Other | 0.0 MW | operational | Goliad, Texas |
| Keys Hollow Storage Phase II SLF | 24INR0066 | Other | 0.0 MW | operational | Goliad, Texas |
| KEYS HOLLOW STORAGE SLF | 24INR0068 | Other | 0.0 MW | operational | Goliad, Texas |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Keys Hollow Solar, LLC | 4 | 402 MW |
| CED Development Inc | 2 | 300 MW |
| Ray Ranch Solar LLC | 1 | 256 MW |
| Double A Storage, LLC | 1 | 0 MW |
| Weser Solar, LLC | 1 | 153 MW |
| SP-Peregrine Solar LLC | 1 | 301 MW |
| Angel City Energy Center, LLC | 1 | 221 MW |
| Kuy Creek Solar 1 LLC | 1 | 235 MW |
| Clip Road Solar LLC | 1 | 204 MW |
| COLETO CREEK POWER LLC | 1 | 655 MW |
| Kuy Creek Storage 1 LLC | 1 | 151 MW |
| Double Lock Solar, LLC | 1 | 133 MW |
| Diablo Campo Energy Center, LLC | 1 | 314 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Goliad County.
Start tracking with interXdata