Knickerbocker Storage is a 25.0 MW other interconnection project in Tom Green, Texas with a current status of suspended. It is proposed to connect at Tap 345kV 76003 Big Hill - 76009 Twin Buttes.

25.0 MWCapacity
SuspendedStatus
ERCOTMarket
OtherTechnology

Project facts

Canonical nameKnickerbocker Storage
Queue ID21INR0446
Statussuspended
Source statussuspended
MarketERCOT
TechnologyOther
Capacity25.0 MW
StateTexas
CountyTom Green
Point of interconnectionTap 345kV 76003 Big Hill - 76009 Twin Buttes
Requested (queue) date2019-12-18
Proposed in-service date2028-06-01
Operational date
Withdrawn date
DeveloperKnickerbocker Solar LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.