Las Lomas Wind Project (63101_WTG)

Las Lomas Wind Project is a 201.6 MW wind interconnection project in Zapata, Texas with a current status of operational.

201.6 MWCapacity
OperationalStatus
ERCOMarket
WindTechnology

Project facts

Canonical nameLas Lomas Wind Project
Queue ID63101_WTG
Statusoperational
Source status(OP) Operating
MarketERCO
TechnologyWind
Capacity201.6 MW
StateTexas
CountyZapata
Point of interconnection
Requested (queue) date
Proposed in-service date
Operational date2020-12-01
Withdrawn date
Developer
Utility / transmission ownerEngie North America

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectoperationalhigh

Explore related data

Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata