Lewis 138 kV is a 240.0 MW battery interconnection project in Atlantic, New Jersey with a current status of withdrawn.

240.0 MWCapacity
WithdrawnStatus
—Market
BatteryTechnology

Project facts

Canonical nameLewis 138 kV
Queue IDAF2-016 - moved to TC1
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyBattery
Capacity240.0 MW
StateNew Jersey
CountyAtlantic
Point of interconnection—
Requested (queue) date2019-10-01
Proposed in-service date2023-05-31
Operational date—
Withdrawn date2024-06-21
Developer—
Utility / transmission ownerAEC

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata