AEC — Interconnection Queue Projects
AEC is associated with 411 tracked interconnection projects representing 25,734 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
411Projects
16Active
34Operational
360Withdrawn
25,734 MWRequested capacity
1Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 83 | 10,698 MW |
| Wind | 29 | 8,099 MW |
| Battery | 42 | 3,466 MW |
| Solar | 253 | 3,412 MW |
| Solar+Battery | 1 | 33 MW |
| Other | 3 | 25 MW |
Portfolio by market
| Market | Projects |
|---|---|
| PJM | 14 |
Geographic footprint
| State | Projects |
|---|---|
| New Jersey | 409 |
| Pennsylvania | 1 |
| Maryland | 1 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Cardiff 230 kV | AE2-251 | Wind | 1,200.0 MW | withdrawn | Monmouth, New Jersey |
| Mickleton 230 kV | A13 | Gas | 803.0 MW | withdrawn | Gloucester, New Jersey |
| Churchtown 230kV | G27 | Gas | 750.0 MW | withdrawn | Salem, New Jersey |
| Cedar 230kV | X1-017 | Wind | 720.0 MW | withdrawn | Atlantic, New Jersey |
| Mickleton 230kV | Q90 | Gas | 650.0 MW | operational | Gloucester, New Jersey |
| Cardiff 230 kV I | AE2-020 | Wind | 604.8 MW | withdrawn | Atlantic, New Jersey |
| Cardiff 230 kV II | AE2-021 | Wind | 604.8 MW | withdrawn | Atlantic, New Jersey |
| Mickleton 230kV | P13 | Gas | 600.0 MW | withdrawn | Gloucester, New Jersey |
| Minotola 138 kV | AB1-169A | Gas | 575.0 MW | withdrawn | Atlantic, New Jersey |
| BL England 138 kV | AF2-169 | Wind | 552.0 MW | withdrawn | Atlantic, New Jersey |
| Churchtown 230kV | Q26 | Gas | 550.0 MW | withdrawn | Salem, New Jersey |
| Mickleton 230kV | S107 | Gas | 520.0 MW | withdrawn | Gloucester, New Jersey |
| New Freedom - Cardiff 230kV | H11 | Gas | 500.0 MW | withdrawn | Gloucester, New Jersey |
| Pedricktown 230kV | A56 | Gas | 500.0 MW | withdrawn | Salem, New Jersey |
| Churchtown-Cumberland 230kV | S122 | Gas | 478.0 MW | withdrawn | Cumberland, New Jersey |
| BL England 138kV | Y1-001 | Gas | 452.0 MW | withdrawn | Cape May, New Jersey |
| Cardiff 230kV | I11 | Gas | 450.0 MW | withdrawn | Atlantic, New Jersey |
| BL England 138 kV | AE2-023 | Wind | 445.2 MW | withdrawn | Atlantic, New Jersey |
| Mickleton 230kV | T123 | Gas | 440.0 MW | withdrawn | Gloucester, New Jersey |
| BL England 138 kV | AE1-104 | Wind | 432.0 MW | suspended | Cape May, New Jersey |
| Orchard 230kV | AH2-333 | Battery | 415.0 MW | withdrawn | Salem, New Jersey |
| Churchtown 230kV 2 | W3-175 | Gas | 371.0 MW | withdrawn | Salem, New Jersey |
| Lewis 138kV | U1-056 | Wind | 350.0 MW | withdrawn | Atlantic, New Jersey |
| Cedar 230kV | T81 | Wind | 350.0 MW | withdrawn | Ocean, New Jersey |
| Corson 138kV | T84 | Wind | 350.0 MW | withdrawn | Cape May, New Jersey |
| Cardiff 230kV | T82 | Wind | 350.0 MW | withdrawn | Atlantic, New Jersey |
| Lewis 138kV | X2-037 | Wind | 350.0 MW | withdrawn | Atlantic, New Jersey |
| England 138kV | G26 | Gas | 350.0 MW | withdrawn | Cape May, New Jersey |
| Merion 138kV | T83 | Wind | 350.0 MW | withdrawn | Atlantic, New Jersey |
| Cedar 230kV | W3-028 | Wind | 348.0 MW | withdrawn | Atlantic, New Jersey |
| England | T146 | Wind | 346.0 MW | withdrawn | Cape May, New Jersey |
| New Freedom - Monroe 230 kV | AH1-260 - moved to TC2 | Battery | 300.0 MW | active | Camden, New Jersey |
| Higbee 69 kV | AE2-222 | Wind | 300.0 MW | withdrawn | Atlantic, New Jersey |
| Cardiff 230 kV III | AE2-022 | Wind | 300.0 MW | withdrawn | Atlantic, New Jersey |
| PJM Queue Project AH1-260 — Battery in Camden, New Jersey | AH1-260 | Battery | 300.0 MW | active | Camden, New Jersey |
| Lewis 138 kV | AF2-016 - moved to TC1 | Battery | 240.0 MW | withdrawn | Atlantic, New Jersey |
| PJM Queue Project AG2-451 — Battery in Salem, New Jersey | AG2-451 | Battery | 240.0 MW | withdrawn | Salem, New Jersey |
| Chambers 230 kV | AG2-451 - moved to TC2 | Battery | 240.0 MW | withdrawn | Salem, New Jersey |
| PJM Queue Project AF2-016 — Battery in Atlantic, New Jersey | AF2-016 | Battery | 240.0 MW | withdrawn | Atlantic, New Jersey |
| Mickleton 230kV 2 | W4-016 | Gas | 235.0 MW | withdrawn | Gloucester, New Jersey |
| Cumberland 230kV | AB2-102 | Gas | 230.0 MW | withdrawn | Cumberland, New Jersey |
| Bridgeport 230 kV | AG2-450 - moved to TC2 | Battery | 219.0 MW | withdrawn | Gloucester, New Jersey |
| PJM Queue Project AG2-450 — Battery in Gloucester, New Jersey | AG2-450 | Battery | 219.0 MW | withdrawn | Gloucester, New Jersey |
| Mickleton 230kV 1 | W4-015 | Gas | 210.0 MW | operational | Gloucester, New Jersey |
| Monroe 138kV | AH2-378A | Battery | 200.0 MW | withdrawn | Gloucester, New Jersey |
| Salem - East Windsor 500kV | H07 | Gas | 200.0 MW | withdrawn | Burlington, New Jersey |
| Churchtown 230kV 1 | W3-174 | Gas | 193.5 MW | withdrawn | Salem, New Jersey |
| Deepwater 138kV | Y2-102 | Gas | 193.0 MW | withdrawn | Salem, New Jersey |
| Cumberland 230 kV | AF1-081 | Solar | 160.0 MW | withdrawn | Atlantic, New Jersey |
| Churchtown 230kV | AA1-108 | Gas | 158.0 MW | withdrawn | Salem, New Jersey |
| Dorothy - Lewis 138 kV | AI2-070 | Battery | 150.0 MW | withdrawn | Atlantic, New Jersey |
| Cardiff | M03 | Gas | 150.0 MW | withdrawn | Atlantic, New Jersey |
| Dorothy - Lewis 138 kV | AI2-071 | Battery | 150.0 MW | withdrawn | Atlantic, New Jersey |
| Deepwater-Upper Pittsgrove 138 kV | AE1-229 | Solar | 149.3 MW | withdrawn | Salem, New Jersey |
| Middle 138kV | P07 | Gas | 122.0 MW | withdrawn | Cape May, New Jersey |
| Missouri Ave | U1-030 | Gas | 110.0 MW | withdrawn | Atlantic, New Jersey |
| Sherman Ave 138kV | U1-029 | Gas | 110.0 MW | withdrawn | Cumberland, New Jersey |
| Cumberland 230 kV | P06 | Gas | 102.0 MW | operational | Cumberland, New Jersey |
| Churchtown-Cumberland 230kV | M14 | Gas | 100.0 MW | withdrawn | Atlantic, New Jersey |
| Cumberland 230 kV | AE2-205 | Solar | 78.0 MW | withdrawn | Cumberland, New Jersey |
| Cardiff 230 kV | AE2-314 | Solar | 72.0 MW | withdrawn | Atlantic, New Jersey |
| Orchard 230kV | W1-011 | Solar | 70.0 MW | withdrawn | Salem, New Jersey |
| Clayville | V2-021 | Gas | 64.0 MW | withdrawn | Cumberland, New Jersey |
| Vineland 69kV | S121 | Gas | 63.0 MW | operational | Cumberland, New Jersey |
| Clayville 69kV | W2-039 | Gas | 63.0 MW | operational | Cumberland, New Jersey |
| Mannington 230 kV | AG2-032 | Solar | 60.0 MW | withdrawn | Salem, New Jersey |
| Gloucester Solar II | AE2-335 | Solar | 60.0 MW | withdrawn | Gloucester, New Jersey |
| Deepwater-Woodstown 69kV | W3-018 | Solar | 60.0 MW | withdrawn | Salem, New Jersey |
| South Millville-Newport 69 kV | AE1-179 | Solar | 59.7 MW | withdrawn | Cumberland, New Jersey |
| Churchtown-Quinton 69 kV | AG1-255 | Solar | 55.0 MW | withdrawn | Salem, New Jersey |
| US Silica - Unimin 69 kV | AG1-129 | Solar | 51.0 MW | withdrawn | Atlantic, New Jersey |
| PJM Queue Project AG2-616 — Solar in Salem, New Jersey | AG2-616 | Solar | 50.0 MW | active | Salem, New Jersey |
| Cumberland 138 kV | AF2-022 | Battery | 50.0 MW | withdrawn | Cumberland, New Jersey |
| Churchtown - Upper Pittsgrove 138 kV | AG2-616 - moved to TC2 | Solar | 50.0 MW | active | Salem, New Jersey |
| Sherman Ave - West Vineland 69 kV | AF1-238 - moved to TC1 | Battery | 50.0 MW | active | Cumberland, New Jersey |
| South Orchard | AF1-238 | Battery | 50.0 MW | active | Cumberland, New Jersey |
| Landis 138 kV | AE1-161 | Battery | 50.0 MW | withdrawn | Cumberland, New Jersey |
| Carlls Corner-Sherman Avenue 69 kV | AE1-240 | Solar | 49.7 MW | withdrawn | Cumberland, New Jersey |
| Roadstown 69 kV | AG2-241 | Solar | 47.0 MW | withdrawn | Cumberland, New Jersey |
| Laurel-Roadstown 69 kV | AF1-208 | Solar | 45.0 MW | withdrawn | Salem, New Jersey |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-08-13 | Ontario 69 kV | status | active | withdrawn |
| 2026-08-06 | Cumberland 230 kV | capacity_mw | 225.0 | 102 |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Track queue activity connecting through AEC.