Lick-Waverly 115kV (AE2-179)

Lick-Waverly 115kV is a 78.0 MW solar interconnection project in Pike, Ohio with a current status of withdrawn.

78.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameLick-Waverly 115kV
Queue IDAE2-179
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity78.0 MW
StateOhio
CountyPike
Point of interconnection—
Requested (queue) date2019-03-18
Proposed in-service date2021-10-31
Operational date—
Withdrawn date2019-04-01
Developer—
Utility / transmission ownerOVEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.