OVEC — Interconnection Queue Projects
OVEC is associated with 10 tracked interconnection projects representing 1,285 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
10Projects
3Active
0Operational
7Withdrawn
1,285 MWRequested capacity
1Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 9 | 1,085 MW |
| Wind | 1 | 200 MW |
Portfolio by market
| Market | Projects |
|---|---|
| PJM | 2 |
Geographic footprint
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| PJM Queue Project AH1-055 — Solar in Jackson, Ohio | AH1-055 | Solar | 220.0 MW | active | Jackson, Ohio |
| Kyger Creek - Don Marquis 345 kV | AH1-055 - moved to TC2 | Solar | 220.0 MW | withdrawn | Jackson, Ohio |
| Keystone-Desoto 345 kV | AF2-388 - moved to TC1 | Wind | 200.0 MW | active | Blackford, Indiana |
| Pierce - Kyger Creek 345 kV | AH1-537 - moved to TC2 | Solar | 178.5 MW | withdrawn | Highland, Ohio |
| PJM Queue Project AH1-537 — Solar in Highland, Ohio | AH1-537 | Solar | 178.5 MW | active | Highland, Ohio |
| Kyger Creek-Pierce 345 kV | AF2-124 | Solar | 120.0 MW | withdrawn | Highland, Ohio |
| Lick-Waverly 115kV | AE2-179 | Solar | 78.0 MW | withdrawn | Pike, Ohio |
| Pierce-Kyger Creek 345 kV | AG2-194 | Solar | 50.0 MW | withdrawn | Highland, Ohio |
| Pierce - Kyger Creek 345 kV | AH1-404 | Solar | 40.0 MW | withdrawn | Highland, Ohio |
| Pierce - Kyger Creek 345 kV | AI2-085 | Solar | 0.0 MW | withdrawn | Highland, Ohio |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-10-01 | Pierce - Kyger Creek 345 kV | proposed_online_date | — | 2028-03-01 |
| 2026-10-01 | Pierce - Kyger Creek 345 kV | withdrawn_date | — | 2026-09-30 |
| 2026-10-01 | Pierce - Kyger Creek 345 kV | status | active | withdrawn |
| 2026-10-01 | Kyger Creek - Don Marquis 345 kV | proposed_online_date | — | 2029-12-31 |
| 2026-10-01 | Kyger Creek - Don Marquis 345 kV | withdrawn_date | — | 2026-09-30 |
| 2026-10-01 | Kyger Creek - Don Marquis 345 kV | status | active | withdrawn |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-10-11
Page data generated2026-10-11
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.