LONG BEACH PEAKER PROJECT (65)

LONG BEACH PEAKER PROJECT is a 424.8 MW gas interconnection project in Los Angeles, California with a current status of withdrawn. It is proposed to connect at Long Beach Gen Station 220kv switchyard.

424.8 MWCapacity
WithdrawnStatus
—Market
GasTechnology

Project facts

Canonical nameLONG BEACH PEAKER PROJECT
Queue ID65
Statuswithdrawn
Source statusWITHDRAWN
Market—
TechnologyGas
Capacity424.8 MW
StateCalifornia
CountyLos Angeles
Point of interconnectionLong Beach Gen Station 220kv switchyard
Requested (queue) date2005-05-06
Proposed in-service date—
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerSCE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.