Lyssy BESS (25INR0597)
Lyssy BESS is a 9.9 MW battery interconnection project in Wilson, Texas with a current status of active. It is proposed to connect at TSP Station Name: LYSSY TSP Station Code: LYSSY Load Name/ Load Transformer Name: Lyssy1 Bus # - PTI Bus Number: #8193 Voltage in kV (Transmission Level): 138 kV Node (associated w/ load/load XFMR in NMMS): 0001.
Project facts
| Canonical name | Lyssy BESS |
|---|---|
| Queue ID | 25INR0597 |
| Status | active |
| Source status | active |
| Market | ERCOT |
| Technology | Battery |
| Capacity | 9.9 MW |
| State | Texas |
| County | Wilson |
| Point of interconnection | TSP Station Name: LYSSY TSP Station Code: LYSSY Load Name/ Load Transformer Name: Lyssy1 Bus # - PTI Bus Number: #8193 Voltage in kV (Transmission Level): 138 kV Node (associated w/ load/load XFMR in NMMS): 0001 |
| Requested (queue) date | — |
| Proposed in-service date | 2026-01-23 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Regis Lyssy LLC |
| Utility / transmission owner | ERCOT |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata