MARATUA SOLAR (22INR0471)

MARATUA SOLAR is a 217.1 MW solar interconnection project in Grimes, Texas with a current status of suspended. It is proposed to connect at Tap 345kV 44645 Singleton – 44660 Skains Ckt 74.

217.1 MWCapacity
SuspendedStatus
ERCOTMarket
SolarTechnology

Project facts

Canonical nameMARATUA SOLAR
Queue ID22INR0471
Statussuspended
Source statussuspended
MarketERCOT
TechnologySolar
Capacity217.1 MW
StateTexas
CountyGrimes
Point of interconnectionTap 345kV 44645 Singleton – 44660 Skains Ckt 74
Requested (queue) date2020-12-02
Proposed in-service date2029-03-31
Operational date
Withdrawn date
DeveloperBDPU Solar Maratua, LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata