Masked (017114)

Masked is a 500.0 MW gas interconnection project in Cleveland, North Carolina with a current status of operational. It is proposed to connect at Dixon School Road Switching Station.

500.0 MWCapacity
OperationalStatus
NCMarket
GasTechnology

Project facts

Canonical nameMasked
Queue ID017114
Statusoperational
Source statusCommercial Operation
MarketNC
TechnologyGas
Capacity500.0 MW
StateNorth Carolina
CountyCleveland
Point of interconnectionDixon School Road Switching Station
Requested (queue) date2013-12-31
Proposed in-service date
Operational date2018-02-07
Withdrawn date
Developer
Utility / transmission ownerDuke Energy Progress

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-24developerNTE Carolinas, LLCMaskedlow
2026-08-03new_projectoperationalhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: duke-dec-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata