Mayberry II BESS (23INR0807)

Mayberry II BESS is a 9.9 MW battery interconnection project in Hidalgo, Texas with a current status of operational. It is proposed to connect at Bus Name: Mayberry, _x000D_ Load name: 1, _x000D_ Bus number: 8109, _x000D_ Voltage: 138kV.

9.9 MWCapacity
OperationalStatus
ERCOTMarket
BatteryTechnology

Project facts

Canonical nameMayberry II BESS
Queue ID23INR0807
Statusoperational
Source statusoperational
MarketERCOT
TechnologyBattery
Capacity9.9 MW
StateTexas
CountyHidalgo
Point of interconnectionBus Name: Mayberry, _x000D_ Load name: 1, _x000D_ Bus number: 8109, _x000D_ Voltage: 138kV
Requested (queue) date2024-01-25
Proposed in-service date2025-01-20
Operational date2025-01-21
Withdrawn date
DeveloperSMT Mission II LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.