McGee Solar (24INR0470)

McGee Solar is a 152.5 MW solar interconnection project in Henderson, Texas with a current status of withdrawn. It is proposed to connect at Bus #6843 at Rayburn Barton Chapel Substation.

152.5 MWCapacity
WithdrawnStatus
ERCOTMarket
SolarTechnology

Project facts

Canonical nameMcGee Solar
Queue ID24INR0470
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologySolar
Capacity152.5 MW
StateTexas
CountyHenderson
Point of interconnectionBus #6843 at Rayburn Barton Chapel Substation
Requested (queue) date2022-11-14
Proposed in-service date2024-12-31
Operational date
Withdrawn date2024-05-03
DeveloperBT McGee Solar, LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata