Meridian BESS (25INR0374)

Meridian BESS is a 31.2 MW battery interconnection project in Bosque, Texas with a current status of active. It is proposed to connect at 319 Meridian 69 KV.

31.2 MWCapacity
ActiveStatus
ERCOTMarket
BatteryTechnology

Project facts

Canonical nameMeridian BESS
Queue ID25INR0374
Statusactive
Source statusactive
MarketERCOT
TechnologyBattery
Capacity31.2 MW
StateTexas
CountyBosque
Point of interconnection319 Meridian 69 KV
Requested (queue) date2023-03-13
Proposed in-service date2027-10-01
Operational date
Withdrawn date
DeveloperNavitas Energy LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.