Middlebrook BESS is a 158.6 MW solar+battery interconnection project in Nacogdoches, Texas with a current status of active. It is proposed to connect at Tap 345kV 3109 Stryker - 3117 Lufkin.

158.6 MWCapacity
ActiveStatus
ERCOTMarket
Solar+BatteryTechnology

Project facts

Canonical nameMiddlebrook BESS
Queue ID25INR0215
Statusactive
Source statusactive
MarketERCOT
TechnologySolar+Battery
Capacity158.6 MW
StateTexas
CountyNacogdoches
Point of interconnectionTap 345kV 3109 Stryker - 3117 Lufkin
Requested (queue) date2022-10-24
Proposed in-service date2027-06-30
Operational date
Withdrawn date
DeveloperMiddlebrook Solar LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata