MISO Queue Project G517 — Wind in Cottonwood, Minnesota

MISO Queue Project G517 — Wind in Cottonwood, Minnesota is a 130.0 MW wind interconnection project in Cottonwood, Minnesota with a current status of withdrawn. It is proposed to connect at Summit Switch Station - South Storden 69 kV line.

130.0 MWCapacity
WithdrawnStatus
MISOMarket
WindTechnology

Project facts

Canonical nameMISO Queue Project G517 — Wind in Cottonwood, Minnesota
Queue IDG517
Statuswithdrawn
Source statuswithdrawn
MarketMISO
TechnologyWind
Capacity130.0 MW
StateMinnesota
CountyCottonwood
Point of interconnectionSummit Switch Station - South Storden 69 kV line
Requested (queue) date2017-06-16
Proposed in-service date2006-10-01
Operational date
Withdrawn date2019-10-24
Developer
Utility / transmission ownerMISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.