MISO Queue Project G569 — Wind in Mercer, Illinois is a 200.0 MW wind interconnection project in Mercer, Illinois with a current status of withdrawn. It is proposed to connect at Galesburg Substation (Knox County).

200.0 MWCapacity
WithdrawnStatus
MISOMarket
WindTechnology

Project facts

Canonical nameMISO Queue Project G569 — Wind in Mercer, Illinois
Queue IDG569
Statuswithdrawn
Source statuswithdrawn
MarketMISO
TechnologyWind
Capacity200.0 MW
StateIllinois
CountyMercer
Point of interconnectionGalesburg Substation (Knox County)
Requested (queue) date2005-11-11
Proposed in-service date2007-11-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerMISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-28

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.