MISO Queue Project G605 — Wind in Montgomery, Indiana

MISO Queue Project G605 — Wind in Montgomery, Indiana is a 200.0 MW wind interconnection project in Montgomery, Indiana with a current status of withdrawn. It is proposed to connect at Crawfordsville - Lafayette SE Switching Station 138 kV.

200.0 MWCapacity
WithdrawnStatus
MISOMarket
WindTechnology

Project facts

Canonical nameMISO Queue Project G605 — Wind in Montgomery, Indiana
Queue IDG605
Statuswithdrawn
Source statuswithdrawn
MarketMISO
TechnologyWind
Capacity200.0 MW
StateIndiana
CountyMontgomery
Point of interconnectionCrawfordsville - Lafayette SE Switching Station 138 kV
Requested (queue) date2006-02-28
Proposed in-service date2008-12-31
Operational date
Withdrawn date2006-09-29
Developer
Utility / transmission ownerMISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-28

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata