MISO Queue Project G629 — Wind in Henry, Illinois

MISO Queue Project G629 — Wind in Henry, Illinois is a 201.0 MW wind interconnection project in Henry, Illinois with a current status of withdrawn. It is proposed to connect at 69 kV line at Geneseo Sub.

201.0 MWCapacity
WithdrawnStatus
MISOMarket
WindTechnology

Project facts

Canonical nameMISO Queue Project G629 — Wind in Henry, Illinois
Queue IDG629
Statuswithdrawn
Source statuswithdrawn
MarketMISO
TechnologyWind
Capacity201.0 MW
StateIllinois
CountyHenry
Point of interconnection69 kV line at Geneseo Sub
Requested (queue) date2006-05-04
Proposed in-service date
Operational date
Withdrawn date2007-04-17
Developer
Utility / transmission ownerMISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.