MISO Queue Project G913 — Wind in Wilkin, Minnesota

MISO Queue Project G913 — Wind in Wilkin, Minnesota is a 201.0 MW wind interconnection project in Wilkin, Minnesota with a current status of withdrawn. It is proposed to connect at 230 kV OTP line.

201.0 MWCapacity
WithdrawnStatus
MISOMarket
WindTechnology

Project facts

Canonical nameMISO Queue Project G913 — Wind in Wilkin, Minnesota
Queue IDG913
Statuswithdrawn
Source statuswithdrawn
MarketMISO
TechnologyWind
Capacity201.0 MW
StateMinnesota
CountyWilkin
Point of interconnection230 kV OTP line
Requested (queue) date2007-11-14
Proposed in-service date2011-11-30
Operational date
Withdrawn date2011-05-04
Developer
Utility / transmission ownerMISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata