MISO Queue Project J002 — Wind in Ford, Illinois

MISO Queue Project J002 — Wind in Ford, Illinois is a 100.0 MW wind interconnection project in Ford, Illinois with a current status of withdrawn. It is proposed to connect at T23N R7E approximately two Miles EAST of the Gibson City South Substation on the Gibson City ?Paxton 138 kV line.

100.0 MWCapacity
WithdrawnStatus
MISOMarket
WindTechnology

Project facts

Canonical nameMISO Queue Project J002 — Wind in Ford, Illinois
Queue IDJ002
Statuswithdrawn
Source statuswithdrawn
MarketMISO
TechnologyWind
Capacity100.0 MW
StateIllinois
CountyFord
Point of interconnectionT23N R7E approximately two Miles EAST of the Gibson City South Substation on the Gibson City ?Paxton 138 kV line
Requested (queue) date2008-10-22
Proposed in-service date2006-10-01
Operational date
Withdrawn date2010-12-22
Developer
Utility / transmission ownerMISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.