MISO Queue Project J434 — Gas in Vermillion, Indiana

MISO Queue Project J434 — Gas in Vermillion, Indiana is a 1,185.0 MW gas interconnection project in Vermillion, Indiana with a current status of withdrawn. It is proposed to connect at Cayuga 345 substation 345 kv bus.

1,185.0 MWCapacity
WithdrawnStatus
MISOMarket
GasTechnology

Project facts

Canonical nameMISO Queue Project J434 — Gas in Vermillion, Indiana
Queue IDJ434
Statuswithdrawn
Source statuswithdrawn
MarketMISO
TechnologyGas
Capacity1,185.0 MW
StateIndiana
CountyVermillion
Point of interconnectionCayuga 345 substation 345 kv bus
Requested (queue) date2015-03-12
Proposed in-service date2019-06-01
Operational date
Withdrawn date2017-06-08
Developer
Utility / transmission ownerMISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata