Monticello 69kV (Acutal POI is a tap on GUERNSEY - Monon Circuit 6907 an appendix G facility) (J2783)

Monticello 69kV (Acutal POI is a tap on GUERNSEY - Monon Circuit 6907 an appendix G facility) is a 33.0 MW solar interconnection project in White, Indiana with a current status of withdrawn. It is proposed to connect at Monticello 69kV (Acutal POI is a tap on GUERNSEY - Monon Circuit 6907 an appendix G facility).

33.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameMonticello 69kV (Acutal POI is a tap on GUERNSEY - Monon Circuit 6907 an appendix G facility)
Queue IDJ2783
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity33.0 MW
StateIndiana
CountyWhite
Point of interconnectionMonticello 69kV (Acutal POI is a tap on GUERNSEY - Monon Circuit 6907 an appendix G facility)
Requested (queue) date2022-09-07
Proposed in-service date2025-01-01
Operational date2025-01-01
Withdrawn date2025-10-27
Developer
Utility / transmission ownerNORTHERN INDIANA PUBLIC SERVICE COMPANY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata