New Underwood Substation 115 kV (GEN-2017-096)

New Underwood Substation 115 kV is a 25.0 MW solar interconnection project in Pennington County, South Dakota with a current status of withdrawn. It is proposed to connect at New Underwood Substation 115 kV.

25.0 MWCapacity
WithdrawnStatus
SDMarket
SolarTechnology

Project facts

Canonical nameNew Underwood Substation 115 kV
Queue IDGEN-2017-096
Statuswithdrawn
Source statusWITHDRAWN
MarketSD
TechnologySolar
Capacity25.0 MW
StateSouth Dakota
CountyPennington County
Point of interconnectionNew Underwood Substation 115 kV
Requested (queue) date2017-05-30
Proposed in-service date
Operational date
Withdrawn date2017-12-14
Developer
Utility / transmission ownerWAPA/BEPC/HCPD Integrated System

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.