NIPSCO Green Acres 138kV Sub (R5067)

NIPSCO Green Acres 138kV Sub is a 100.0 MW battery interconnection project in Lake, Indiana with a current status of active. It is proposed to connect at NIPSCO Green Acres 138kV Sub.

100.0 MWCapacity
ActiveStatus
Market
BatteryTechnology

Project facts

Canonical nameNIPSCO Green Acres 138kV Sub
Queue IDR5067
Statusactive
Source statusActive
Market
TechnologyBattery
Capacity100.0 MW
StateIndiana
CountyLake
Point of interconnectionNIPSCO Green Acres 138kV Sub
Requested (queue) date2025-07-03
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerNORTHERN INDIANA PUBLIC SERVICE COMPANY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.