Nittany North Solar (AH1-313)

Nittany North Solar is a 100.0 MW solar+battery interconnection project in Centre, Pennsylvania with a current status of withdrawn. It is proposed to connect at Moshannon-Milesburg 230 kV VII.

100.0 MWCapacity
WithdrawnStatus
PJMMarket
Solar+BatteryTechnology

Project facts

Canonical nameNittany North Solar
Queue IDAH1-313
Statuswithdrawn
Source statuswithdrawn
MarketPJM
TechnologySolar+Battery
Capacity100.0 MW
StatePennsylvania
CountyCentre
Point of interconnectionMoshannon-Milesburg 230 kV VII
Requested (queue) date2025-02-14
Proposed in-service date2025-12-31
Operational date
Withdrawn date2025-12-03
DeveloperInvenergy
Utility / transmission ownerAPS

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata