NOT IN DROPDOWN MENU (J3549)
NOT IN DROPDOWN MENU is a 484.5 MW gas interconnection project in Mower, Minnesota with a current status of withdrawn. It is proposed to connect at NOT IN DROPDOWN MENU.
484.5 MWCapacity
WithdrawnStatus
—Market
GasTechnology
Project facts
| Canonical name | NOT IN DROPDOWN MENU |
|---|---|
| Queue ID | J3549 |
| Status | withdrawn |
| Source status | Withdrawn |
| Market | — |
| Technology | Gas |
| Capacity | 484.5 MW |
| State | Minnesota |
| County | Mower |
| Point of interconnection | NOT IN DROPDOWN MENU |
| Requested (queue) date | 2024-04-17 |
| Proposed in-service date | 2026-06-01 |
| Operational date | 2026-06-01 |
| Withdrawn date | 2025-12-23 |
| Developer | — |
| Utility / transmission owner | GREAT RIVER ENERGY |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata