Oasis wind (29INR0073)
Oasis wind is a 300.0 MW other interconnection project in Crockett, Texas with a current status of active. It is proposed to connect at 6562 Friend Ranch Station 138kV.
300.0 MWCapacity
ActiveStatus
CrockettMarket
OtherTechnology
Project facts
| Canonical name | Oasis wind |
|---|---|
| Queue ID | 29INR0073 |
| Status | active |
| Source status | SS Started, FIS Started, No IA |
| Market | Crockett |
| Technology | Other |
| Capacity | 300.0 MW |
| State | Texas |
| County | Crockett |
| Point of interconnection | 6562 Friend Ranch Station 138kV |
| Requested (queue) date | 2026-07-22 |
| Proposed in-service date | 2030-07-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Nextera |
| Utility / transmission owner | ERCOT |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-31 | new_project | — | active | high |
Explore related data
Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-11
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata