OCI SunRoper MW Increase to 24INR0167 (25INR0291)

OCI SunRoper MW Increase to 24INR0167 is a 61.6 MW solar interconnection project in Wharton, Texas with a current status of withdrawn. It is proposed to connect at tap138kV #43190 South Lane City to #42985 Dyann CKT#60.

61.6 MWCapacity
WithdrawnStatus
ERCOTMarket
SolarTechnology

Project facts

Canonical nameOCI SunRoper MW Increase to 24INR0167
Queue ID25INR0291
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologySolar
Capacity61.6 MW
StateTexas
CountyWharton
Point of interconnectiontap138kV #43190 South Lane City to #42985 Dyann CKT#60
Requested (queue) date
Proposed in-service date2025-06-01
Operational date
Withdrawn date2023-10-31
DeveloperOCI SunRoper LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata