Ontario 69 kV (AF2-025 - moved to TC1)

Ontario 69 kV is a 20.0 MW battery interconnection project in Atlantic, New Jersey with a current status of withdrawn.

20.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameOntario 69 kV
Queue IDAF2-025 - moved to TC1
Statuswithdrawn
Source statusPending Termination
Market
TechnologyBattery
Capacity20.0 MW
StateNew Jersey
CountyAtlantic
Point of interconnection
Requested (queue) date2019-11-15
Proposed in-service date2029-04-30
Operational date
Withdrawn date
Developer
Utility / transmission ownerAEC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-13statusactivewithdrawnhigh
2026-08-01proposed_online_date2028-04-302029-04-30medium
2026-07-29new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.