Pecos Flats Solar III (29INR0181)

Pecos Flats Solar III is a 304.0 MW solar interconnection project in Pecos, Texas with a current status of operational. It is proposed to connect at 60404 SOLSTICE 345 kV.

304.0 MWCapacity
OperationalStatus
PecosMarket
SolarTechnology

Project facts

Canonical namePecos Flats Solar III
Queue ID29INR0181
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketPecos
TechnologySolar
Capacity304.0 MW
StateTexas
CountyPecos
Point of interconnection60404 SOLSTICE 345 kV
Requested (queue) date2025-09-22
Proposed in-service date
Operational date2029-10-20
Withdrawn date
DeveloperGlass Mountain Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata