Penniman - Waller 230 kV (AH1-157 - moved to TC2)

Penniman - Waller 230 kV is a 100.0 MW battery interconnection project in York, Virginia with a current status of withdrawn.

100.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical namePenniman - Waller 230 kV
Queue IDAH1-157 - moved to TC2
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity100.0 MW
StateVirginia
CountyYork
Point of interconnection
Requested (queue) date2021-08-31
Proposed in-service date2027-12-01
Operational date
Withdrawn date2025-11-19
Developer
Utility / transmission ownerDominion

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.