Petty to Chapel 138 kV Line (GEN-2023-227)

Petty to Chapel 138 kV Line is a 200.0 MW battery interconnection project in Titus, Texas with a current status of withdrawn. It is proposed to connect at Petty to Chapel 138 kV Line.

200.0 MWCapacity
WithdrawnStatus
TXMarket
BatteryTechnology

Project facts

Canonical namePetty to Chapel 138 kV Line
Queue IDGEN-2023-227
Statuswithdrawn
Source statusWITHDRAWN
MarketTX
TechnologyBattery
Capacity200.0 MW
StateTexas
CountyTitus
Point of interconnectionPetty to Chapel 138 kV Line
Requested (queue) date2023-10-02
Proposed in-service date2026-09-01
Operational date
Withdrawn date2025-08-25
Developer
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata