Titus County, Texas — Interconnection Projects

The interXdata warehouse tracks 6 interconnection projects in Titus, Texas, representing 1,959 MW of requested capacity.

6Total projects
1Active
2Operational
3Withdrawn
1,959 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Other21,116 MW
Battery3603 MW
Solar1240 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Welsh6139_1Other558.0 MWoperationalTitus, Texas
Welsh6139_3Other558.0 MWoperationalTitus, Texas
Welsh-Lydia 345kV Line BreakGEN-2021-055Solar240.0 MWwithdrawnTitus, Texas
Wekiva Grid23INR0067Battery202.6 MWwithdrawnTitus, Texas
Petty to Chapel 138 kV LineGEN-2023-227Battery200.0 MWwithdrawnTitus, Texas
Welsh 345kV SubstationGEN-2021-038Battery200.0 MWactiveTitus, Texas

Top developers

Developer (canonical)ProjectsCapacity
Wekiva Grid, LLC1203 MW

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.