PG&E DG PGE-INT-112583515 (PGE-INT-112583515)

PG&E DG PGE-INT-112583515 is a 2.1 MW solar interconnection project in Fresno, California with a current status of operational.

2.1 MWCapacity
OperationalStatus
FRESNOMarket
SolarTechnology

Project facts

Canonical namePG&E DG PGE-INT-112583515
Queue IDPGE-INT-112583515
Statusoperational
Source statusInterconnected
MarketFRESNO
TechnologySolar
Capacity2.1 MW
StateCalifornia
CountyFresno
Point of interconnection
Requested (queue) date2017-01-31
Proposed in-service date
Operational date2018-09-14
Withdrawn date
DeveloperSunEdison
Utility / transmission ownerPG&E

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: ca-dgstats. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata