Pinewood - St Johns 115 kV II (AH1-168)

Pinewood - St Johns 115 kV II is a 40.0 MW solar interconnection project in Caroline, Virginia with a current status of withdrawn.

40.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical namePinewood - St Johns 115 kV II
Queue IDAH1-168
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity40.0 MW
StateVirginia
CountyCaroline
Point of interconnection
Requested (queue) date2021-08-27
Proposed in-service date2026-06-01
Operational date
Withdrawn date2024-12-18
Developer
Utility / transmission ownerDominion

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-28

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.