Pinewood - St. Johns 115 kV (AH1-103)

Pinewood - St. Johns 115 kV is a 75.0 MW solar interconnection project in Caroline, Virginia with a current status of withdrawn.

75.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical namePinewood - St. Johns 115 kV
Queue IDAH1-103
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity75.0 MW
StateVirginia
CountyCaroline
Point of interconnection
Requested (queue) date2021-08-02
Proposed in-service date2025-06-01
Operational date
Withdrawn date2024-01-10
Developer
Utility / transmission ownerDominion

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata