PJM Queue Project AH1-729 — Battery in Loudoun, Virginia

PJM Queue Project AH1-729 — Battery in Loudoun, Virginia is a 100.0 MW battery interconnection project in Loudoun, Virginia with a current status of withdrawn. It is proposed to connect at Ocean Court 230 kV.

100.0 MWCapacity
WithdrawnStatus
PJMMarket
BatteryTechnology

Project facts

Canonical namePJM Queue Project AH1-729 — Battery in Loudoun, Virginia
Queue IDAH1-729
Statuswithdrawn
Source statuswithdrawn
MarketPJM
TechnologyBattery
Capacity100.0 MW
StateVirginia
CountyLoudoun
Point of interconnectionOcean Court 230 kV
Requested (queue) date2025-04-08
Proposed in-service date
Operational date
Withdrawn date2025-12-02
DeveloperGSP Sterling Project I, LLC
Utility / transmission ownerDominion

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata