PowerVault BESS is a 254.8 MW other interconnection project in McLennan, Texas with a current status of operational. It is proposed to connect at Tap 345kV 3406 Elm Mott - 3405 Tradinghouse Ses.

254.8 MWCapacity
OperationalStatus
McLennanMarket
OtherTechnology

Project facts

Canonical namePowerVault BESS
Queue ID26INR0422
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketMcLennan
TechnologyOther
Capacity254.8 MW
StateTexas
CountyMcLennan
Point of interconnectionTap 345kV 3406 Elm Mott - 3405 Tradinghouse Ses
Requested (queue) date2024-03-22
Proposed in-service date
Operational date2027-07-01
Withdrawn date
DeveloperSMT Elm Mott BESS
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata