PJM Queue Project AH2-407 — Solar in New Castle, Delaware

PJM Queue Project AH2-407 — Solar in New Castle, Delaware is a 34.5 MW solar interconnection project in New Castle, Delaware with a current status of withdrawn.

34.5 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical namePJM Queue Project AH2-407 — Solar in New Castle, Delaware
Queue IDAH2-407
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity34.5 MW
StateDelaware
CountyNew Castle
Point of interconnection
Requested (queue) date2022-03-10
Proposed in-service date2027-09-24
Operational date
Withdrawn date2022-04-11
Developer
Utility / transmission ownerDPL

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.