Providence Forge-Turner 115kV (AH1-042 - moved to TC2)

Providence Forge-Turner 115kV is a 154.0 MW solar interconnection project in Charles City, Virginia with a current status of withdrawn.

154.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameProvidence Forge-Turner 115kV
Queue IDAH1-042 - moved to TC2
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity154.0 MW
StateVirginia
CountyCharles City
Point of interconnection—
Requested (queue) date2021-06-25
Proposed in-service date2029-09-30
Operational date—
Withdrawn date2025-12-02
Developer—
Utility / transmission ownerDominion

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.