Red Lion 138kV (X1-097)

Red Lion 138kV is a 24.9 MW other interconnection project in New Castle, Delaware with a current status of operational.

24.9 MWCapacity
OperationalStatus
Market
OtherTechnology

Project facts

Canonical nameRed Lion 138kV
Queue IDX1-097
Statusoperational
Source statusIn Service
Market
TechnologyOther
Capacity24.9 MW
StateDelaware
CountyNew Castle
Point of interconnection
Requested (queue) date2011-04-29
Proposed in-service date
Operational date2013-03-15
Withdrawn date
Developer
Utility / transmission ownerDPL

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata