RIO SECO WIND (277)

RIO SECO WIND is a 75.0 MW wind interconnection project in San Bernardino, California with a current status of withdrawn. It is proposed to connect at Coolwater-Dunn Siding 115kV line.

75.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameRIO SECO WIND
Queue ID277
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologyWind
Capacity75.0 MW
StateCalifornia
CountySan Bernardino
Point of interconnectionCoolwater-Dunn Siding 115kV line
Requested (queue) date2007-11-15
Proposed in-service date
Operational date
Withdrawn date2008-03-06
Developer
Utility / transmission ownerSCE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata