S_Hills Wind (12INR0055)
S_Hills Wind is a 30.2 MW wind interconnection project in Baylor, Texas with a current status of operational. It is proposed to connect at 33728 Mabelle 69kV.
30.2 MWCapacity
OperationalStatus
ERCOTMarket
WindTechnology
Project facts
| Canonical name | S_Hills Wind |
|---|---|
| Queue ID | 12INR0055 |
| Status | operational |
| Source status | operational |
| Market | ERCOT |
| Technology | Wind |
| Capacity | 30.2 MW |
| State | Texas |
| County | Baylor |
| Point of interconnection | 33728 Mabelle 69kV |
| Requested (queue) date | 2010-09-27 |
| Proposed in-service date | 2019-07-31 |
| Operational date | 2019-08-07 |
| Withdrawn date | — |
| Developer | SEYMOUR HILLS WIND PROJECT, LLC |
| Utility / transmission owner | ERCOT |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.